Subject: SPALLING REPAIR SCHEDULE

 

This schedule was revised Saturday, March 24, 2007.    This schedule will change often as we know more.
 
As you know, we have had two crews  operating two scaffolds.  The first crew had only the "01" stack and has completed spalling repairs to all decks that were found to have damage.  They have also completed on stack "01" all damage found on the inside and outside of front walls, the railing posts, leading edges, Ewa end wall and divider wall with the "02" stack.  They will be moving on Monday 3/26/07 to the "13" & "14" stacks. 
 
The second crew on the "02" & "03" stack has five to six more days work remaining on those stacks.  They will
then move to the "12" stack.

 

                     1 bedroom units                                                                               2 bedroom units

               13 & 14 stack    -      March 27 to May 15                   06 stack & end wall    -      Sept 13 to Oct 11

               12 stack          -         April 3 to May 15                        07 stack & end wall    -      Oct 11 to Nov 8

               09, 10 & 11 stack -   May 16 to June 27                       01 and 02 stack          -      Nov 9 to Dec. 7

               06, 07 & 08 stack -   June 28 to August 13                   03 stack & end wall    -       Dec. 10 to Jan. 8

               04 & 05 stack     -     August 14 to Sept 12                   04 and 05 stack          -       Jan 9 to Feb 12

 